4 Aug 03:42:00
[Broadband and Ethernet] Core switch configuration changes - Completed
Details
Posted: 2 Aug 16:44:03
Between 2am and 3am we will be making changes to the configuration of our core switches, this will be to aid in our diagnostics in regards to the MSO that occurred in July. We expect there to be a few short disruptions to routing and there may be a PPP drop or two for some customers during this window.
Update
4 Aug 02:01:23
This work is about to commence.
Update
4 Aug 02:40:56
We have four small jobs to do, the first has been completed without any disruption. We're moving the estimated completion time to 4AM though, so as to give us a bit more time.
Update
4 Aug 02:58:57
The second job has been completed without any disruption.
Update
4 Aug 03:21:34
The third job has been completed, it did cause some routing issues for around 10 minutes.
Resolution This work has been completed.
Started 4 Aug 02:00:00
Closed 4 Aug 03:42:00
Previously expected 4 Aug 03:00:00