Due to Netezza performance issues on the COBAL_ODS Database, all the FLASH dependent jobs are still pending.::WO0000000046298
MINOR Assumed Closed TTB-Outages
STATUS
Assumed Closed
CREATED
May 07, 03:10 PM (5 years ago)
TYPE
TalkTalk Outage
STARTED
May 07, 02:09 PM (5 years ago)
EXPECTED CLOSED
May 07, 05:00 PM (5 years ago)
REFERENCE
34901 / INC13326574
INFORMATION
  • INITIAL
    5 years ago

    Summary
    CGI have advised that due to performance issues being seen on Netezza today, some FLASH dependent jobs are still pending. This is due to the fact that the queries executed in them not fetching the required data. This is impacting on DWH data loading and 50% of the ETL Load has been confirmed as incomplete.
    
    N/A
                              

  • UPDATE
    5 years ago

    Latest Update MIM, DWH Operations and IBM are still on a conference bridge working through. IBM have advised a reboot of the Netezza database service is required to restore service. This is impacting the delivery of business critical reports. The following reports are impacted: Dimension , Fact, Package, product, Supplementary Services, Order, Orderline, Prov CMD, Online & handset, Car. An outage period of 30 minutes will be experienced during the reboot of the service. Impacted users have been advised of the downtime outage while works are completed. The service restart commenced at 15:00  

  • NEXT UPDATE...

    Due 5 years ago (overdue)