Service Impacting (Due Mon 20 September 21) :CRQ000000100286 : : TTB Planned Works Notification :: Internal Initial::Exchange Delivery - R11 Upgrades - MYSNH MYWAK NDASF NDBAT :: CRQ000000100286::WO0000000071789
MAINTENANCE Assumed Completed TTB-PEW
STATUS
Assumed Completed
CREATED
Sep 03, 02:10 PM (3¾ years ago)
TYPE
TalkTalk Maintenance
STARTED
Sep 20, 12:05 AM (3¾ years ago)
EXPECTED CLOSED
Sep 20, 06:00 AM (3¾ years ago)
REFERENCE
41812 / CRQ000000100286
INFORMATION
  • INITIAL
    3¾ years ago

    Overview of Work
    Impacted Services:  DSL  EFM  EAD  EoFTTC FTTC FTTP - OR
    ++++++++++++++++++++++++++++
    Exchange Delivery - R11 Upgrades - MYSNH MYWAK NDASF NDBAT :: CRQ000000100286
    Overview of Work: 
     Metro Switch Firmware Upgrade NE40-M2F
    The exchange switch is the main interface of our customers and our network at the exchange level. This RFC is to upgrade the firmware of main exchange metro switch pair NE40-M2F to the newer firmware version which is recommended by the vendor Huawei. 
    All voice; data and TV services on the exchange with resilience will failover for the duration of the work as such there will no service impact. Services without resilience will experience downtime when device reboots. These devices are installed in pairs and one device will be rebooted at a time to keep customer downtime to the minimum.
    Testing is completed following the change to ensure services have resumed. Testing  http://testingplatform.noc.cpwn.lan/juniperswapout.php
    Impact of your change: TalkTalk Network; TalkTalk Business; TTB Reseller; Customers will be affected during the change. Ashford Battle Snaith Wakefield
                              

  • Closed